| Sl.No |
DSR Item No & Page No. |
Description |
Unit |
Qty |
Rate |
Amount in Rupees |
| 1 |
-
| | 17.47A.1 /183 | 17.47A.2 /183
| |
| Providing and applying tack coat using hot straight run bitumen of grade 80 / 100 including heating the bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing road surface as per specifications - On W.B.M @ 0.75 kg / sqm.
| | (a) on W.B.M., @ 0.75 Kg / Sqm | | (b) On bitumen surface @ 0.50 Kg / Sqm |
|
Sqm
Sqm |
500.00
13544.00
|
11.50
8.45 |
5750.00
114446.80 |
| 2 |
17.49.2 / 184 |
2.5 cm premix carpet surfacing with 2.25 cum and 1.12 cum of stone chipppings of 13.2 mm and 11.2 mm size respectively per 100 sqm and 52 kg and 56 kg ofhot bitumen per cumof stone chippings of 13.2 and 11.2 mm size respectively including a tack coat with hot straight run bitumen including consolidation with road roller of 6 to 9 tonne capacity etc., complete (tack coat to be paid for separately) - |
Sqm |
14044.00 |
51.95 |
729585.80 |
| 3 |
17.59 / 186 |
Providing and laying seal coat of premixed fine aggreage ( passing 2.36 mm and retained on 180 micron sieve) with bitumen using 128 kg of bitumen of grade 80 / 100 bitumen per cum of fine aggregate and 0.60 cum of fine aggregate per 100 sqm of road surface including rolling and finising with road roller all complete. |
Sqm |
14044.00 |
19.30 |
271049.20 |
| 4 |
17.52.1 / 184 |
Providing and laying premix bituminous macadam base course with stone agregate of quality size and grading as specified in CPWD specification and straight run bitumen of grade 80 / 100 @ 5% by weight of total mix including hot mixing of stone aggregate and bitumen in hot mix plant, transporting mixed material and laying mixed material with paver finisher to the required level and grade, rolling with road roller of 8 to 10 tonne capcity to achieve the required compaction and denisty - 75 mm compacted thickness. |
Sqm |
15.00 |
2268.20 |
34023.00 |
| - |
- |
Sub Total in Rs. |
- |
- |
- |
1154854.80 |
| - |
- |
Add cost index @ (215 - 166 % 166 ) x 100 = 29.51%
|
- |
- |
- |
340797.65
|
| - |
- |
Total in Rs. |
- |
- |
- |
1495652.45
|
| - |
- |
Total Amount rounded to in Rs.
|
- |
- |
- |
14,95,652.00
|